University of Connecticut, South Campus Express Line Water Distribution Main

BL Companies provided engineering design services to the University of Connecticut for the preparation of designs, cost estimates, construction documents, and assistance in the bidding process for the extension of the South Campus Express Line Water Distribution Main from Bolton Road to Willowbrook Road, via Dog Lane.
 
This project involves the design of approximately 600 linear feet of 12” diameter water distribution main (Express Line) from the existing water main in Bolton Road across Storrs Road to serve the proposed Storrs Center, and the design of approximately 1,050 linear feet of 8” diameter water main (Dog Lane Loop) to the existing water main in Willowbrook Road to create a looped system. The Express Line and the Loop was constructed in phases and bid as two separate construction contracts.

University of Connecticut, South Campus Express Line Water Distribution Main was last modified: October 16th, 2014 by BL Companies