New Fairfield High School

BL Companies produced a master plan of long term improvements and required renovations to the existing 264,000 SF middle and high school complex that houses grades 6 through 8 and 9 through 12, respectively. The first phase of the project involved the renovation of approximately 20,000 SF of the 30,000 SF third floor academic wing. The renovations included new science labs, prep rooms, classrooms and toilet facilities, MEP systems and finishes. Future improvements may include an enlarged cafeteria, improved circulation, new entrance, new administration area, and auditorium renovations. New program spaces may include additional classrooms, family and consumer science rooms and middle school media center.

Phase 1 was completed over the summer of 2010 on time and $50,000 under budget. Since 2010, BL Companies has also provided design services for toilet and ADA renovations.

Project budget $5,000,000
Renovated area 20,000 SF

New Fairfield High School was last modified: October 7th, 2014 by BL Companies